Dear NetKL's valued clients,
Please be informed, that TM Brickfield Datacenter is going to perform preventive Power Maintenance and Power Upgrading Work on 10th & 20th August 2011 (refer their email below)

1) Date : 10th August 2011 (Wednesday)
Start Time: 00:01am
End Time: 02:00 am
Remarks : They expect no effect to the servers, hence, no downtime is expected.

2) Date : 20th August 2011 (Saturday)
Start Time: 00:01am
End Time: 06:00 am
Remarks : The servers will be shut down, hence, there will be downtime.

According to them, this preventive maintenance work is vital to prevent sudden power outage in their datacenter, for our own convenience in future.

Thanks a lot for your co-operation & understanding.

Best regards,

Support Team
NetKL Network



----- Original Message -----
From: TM's Brickfield datacenter
To : All clients
Sent: Tuesday, August 02, 2011 7:42 AM
Subject: Announcement : Power Maintenance and Power Upgrading Work at TM Data Center BRICKFIELD on 10th & 20th August 2011


Dear Valued Customers and Partners,
Thank you for your continued support towards TM Data Center BRICKFIELD.

In order to serve you better on your future power requirement, please be advised of the following Planned Power Maintenance and Power upgrading Activities to the building TM Brickfield jointly conducted by TNB, TM Properties Operations and Data Center Management.

To Carryout Planned Power Maintenance and Power Upgrading Work at TM Data Center BRICKFIELD


1) Date : Wednesday , 10th August 2011
Start Time: 00:01am
End Time: 02:00 am

2) Date : Saturday , 20th August 2011
Start Time: 00:01am
End Time: 06:00 am


We would like to apologize for any inconvenience this may cause. Please do not hesitate to contact us if you have any questions or concerns about this planned maintenance activities.


Your co-operation is highly appreciated.

Thank you & Regards,


TM's Brickfield Datacenter,
Kuala Lumpur



Wednesday, August 3, 2011